Dear;

           I have a cisco cmts ubr7246vxr with plates m28u and ios ubr7200-jk9su2-mz.122-33.SCD7. I'm trying to do the configuration for downstream bonding for bronze certification. part to configure an RCC-TEMPLATE have no problems appear all commands but when I apply the interface cable can not find the command. see section "Assigning an RCC Template to a Cable Interface" file attachment. do you have any idea why this is?

Thank you, Flavio.

husamaga
Did you tryed with command:

Did you tryed with command:
controller integrated-cable 1/1 ?

Killa200
Wait am I missing something?

Wait am I missing something? The MC28u is not a docsis 3.0 card, but your trying to do bonding? Yet the cisco doc you reference actually shows that card as a docsis 3 bonding option? Is the card hiding something i don't know about, or is cisco being vague again?

flavio.mali
Bonding Bronze

I know that the card m28u is not docsis 3.0. see article link below. I'm trying to configure DOCSIS 3.0 Downstream Bonding for Bronze Certification.

http://www.cedmagazine.com/articles/2006/05/docsis-2.0b

flavio.mali
Bonding Bronze

Thanks for the help. I found this command. WHAT have are in attachments.

* RCC-TEMPLATE.jpg - initial configuration for bonding

* INTERFACE.jpg - No Integraded interface

* INTERFACE_CABLE.jpg - Meeting this command but I can not implement the interface.

best regards, Flavio.